Syrian Electricity Company Signs 639 MW Aleppo Thermal Plant Rehabilitation Deal

Syria's state electricity company signed an agreement with Czech firm Energy Care to rehabilitate the second, third and fourth generating units at Aleppo thermal power plant, with a combined capacity of 639 megawatts. The signing took place at the Ministry of Energy building in Damascus.

This article is shown in English; SYPNow publishes its newsroom in Arabic and English only.

Signing ceremony at the Syrian Ministry of Energy in Damascus between delegations of the Syrian electricity company and a Czech company

Key points

  • Agreement signed at the Ministry of Energy in Damascus.
  • Covers units two, three and four at Aleppo thermal power plant.
  • Combined capacity of the covered units is 639 megawatts.
  • Implementing partner is Czech company Energy Care.
  • The deal is rehabilitation, not immediate operation; no timeline announced.

What Was Signed at Syria's Energy Ministry

Syria's official news agency SANA reported that the Syrian Electricity Company signed an agreement with Czech company Energy Care to rehabilitate the second, third and fourth generating units at Aleppo thermal power plant, with a total capacity of 639 megawatts. The signing ceremony took place at the Ministry of Energy building in Damascus.

For readers unfamiliar with Syria's energy situation: the national grid suffers from a severe generation shortfall built up over years of conflict, resulting in only a few hours of state electricity per day in most areas. Aleppo's thermal plant is one of the country's major generating facilities, so any restoration of its units matters nationally.

Scope of the Aleppo Plant Rehabilitation

The agreement specifically covers units two, three and four of the plant, not the first unit or other assets. The combined capacity of the three covered units is 639 megawatts, a figure tied to the units' design capacity as stated in the deal.

Thermal plant rehabilitation typically involves major overhauls and repair or replacement of equipment to restore generation capacity. Such work generally runs over extended periods and does not translate into immediate power output.

What This Means for Syrians

For residents of Aleppo and other governorates, the announcement signals an intent to recover lost generation capacity, but it does not mean an immediate improvement in daily electricity hours. No implementation timeline has been announced, nor details on the contract's cost or financing arrangements.

The involvement of a Czech company points to a gradual return of foreign firms to Syria's energy sector, a development closely watched by the diaspora and potential investors, given that power is among the sectors most in need of reconstruction funding.

Open Questions After the Signing

Key details remain undisclosed: start dates and duration of the works, total contract cost, financing sources, and how rehabilitation will proceed while parts of the plant are still needed for operation. It is also unclear whether follow-on contracts covering other units or plants are planned.

Syrians who currently rely on solar panels and private generators will be watching whether this deal marks the start of a broader effort to rebuild the country's generation sector.

Frequently asked questions

What capacity is covered by the Aleppo plant rehabilitation deal

The agreement covers units two, three and four at Aleppo thermal power plant, with a combined capacity of 639 megawatts. Syria's state electricity company signed it with Czech firm Energy Care at the Ministry of Energy in Damascus.

Which company will rehabilitate Aleppo thermal power plant

Czech company Energy Care is the implementing partner. It signed the agreement with the Syrian Electricity Company at the Ministry of Energy building in Damascus to rehabilitate the plant's second, third and fourth units.

When will the Aleppo plant rehabilitation be completed

No timeline has been announced. The agreement covers rehabilitation rather than immediate operation, and the announced details include no start date or completion date for the works.

Will electricity supply improve in Aleppo soon

Not immediately. The deal concerns rehabilitating generating units totaling 639 megawatts, work that will take an unspecified period. The signing does not directly translate into more daily power hours.

More news

Today's Syrian pound rate

Live buy, sell and mid rates, measured and published by SYPNow.

See the rates

SYPNow reports news from the sources it names. Exchange rates quoted anywhere on this site come from SYPNow's own measurement, never from a third-party bulletin.